Control Room & Scheduler

Expand all | Collapse all

Exporting histroy of a process Control Room

  • 1.  Exporting histroy of a process Control Room

    Posted 08-05-2019 11:45
    Does anyone know if there is a way to Export the full history of your Blue Prism Process from the Control Room? 

    We have obtained a performance trend template from Blue Prism and would like to paste in the data.

    Thanks

    ------------------------------
    Alex Francis
    RPA Developer
    Swinton Insurance
    ------------------------------


  • 2.  RE: Exporting histroy of a process Control Room

    Posted 08-05-2019 14:05
    There are several views in Control Room. Are you referring to session logs?

    ------------------------------
    Dave Morris
    3Ci @ Southern Company
    Atlanta, GA
    ------------------------------



  • 3.  RE: Exporting histroy of a process Control Room

    Posted 08-05-2019 14:26
    Hi David,

    So i need the following information for the entrie history of the work queue:

    Id KeyValue Priority Status Tags Resource Attempt Loaded LastUpdated Deferred Locked Completed Worktime Exception ExceptionReason

    Will it have to be an MI Report?

    ------------------------------
    Alex Francis
    RPA Developer
    Swinton Insurance
    ------------------------------



  • 4.  RE: Exporting histroy of a process Control Room

    Posted 08-05-2019 14:31
    I see. Go to the work queue in Control Room and right click on a queue item, and then click 'Export Current View as Report'. That'll give you several options for how much to export. The third option should output everything.

    ------------------------------
    Dave Morris
    3Ci @ Southern Company
    Atlanta, GA
    ------------------------------