    <title>topic Workqueue Item - Total Worktime Limitation in Product Forum</title>
    <link>https://community.blueprism.com/t5/Product-Forum/Workqueue-Item-Total-Worktime-Limitation/m-p/63858#M16727</link>
    <description>&lt;P&gt;&lt;SPAN&gt;We found that a limitation of Blue Prism is that it does not capture that any work (ie worktime) has been performed on a workqueue item when it is put back to the queue as 'Pending'.&amp;nbsp;&lt;/SPAN&gt;&lt;/P&gt;
&lt;P&gt;&lt;SPAN&gt;In other words, Blue Prism does not account for worktime on a Queue Item if it is locked, processed partially, and subsequently unlocked without marking it as Completed or Exception. The 'worktime' field within the BPAWorkQueueItem Database table&amp;nbsp;only accounts for the last touchpoint of any workqueue item (the time between the Start Time of the 'Get Next Item' action and the End Time of the 'Mark Complete' / 'Mark Exception' actions)&lt;BR /&gt;&lt;BR /&gt;&lt;/SPAN&gt;Unfortunately, this means that we can't accurately determine how long it took to process a workqueue Item if it is touched (picked from the queue) multiple times.&lt;BR /&gt;&lt;BR /&gt;&lt;SPAN lang="en-US"&gt;&lt;SPAN&gt;Can an enhancement be made to the product such that the Worktime field from the BPAWorkQueueItem table accounts for all time where the item was locked?&lt;BR /&gt;&lt;/SPAN&gt;&lt;/SPAN&gt;&lt;BR /&gt;Thank You&lt;/P&gt;&lt;BR /&gt;&lt;BR /&gt;------------------------------&lt;BR /&gt;Nicolas Payeur&lt;BR /&gt;Manager&lt;BR /&gt;Reveal Group&lt;BR /&gt;America/New_York&lt;BR /&gt;------------------------------&lt;BR /&gt;</description>
    <pubDate>Wed, 23 Sep 2020 16:24:00 GMT</pubDate>
    <dc:creator>nicolas.payeur</dc:creator>
    <dc:date>2020-09-23T16:24:00Z</dc:date>
    <item>
      <title>Workqueue Item - Total Worktime Limitation</title>
      <link>https://community.blueprism.com/t5/Product-Forum/Workqueue-Item-Total-Worktime-Limitation/m-p/63858#M16727</link>
      <description>&lt;P&gt;&lt;SPAN&gt;We found that a limitation of Blue Prism is that it does not capture that any work (ie worktime) has been performed on a workqueue item when it is put back to the queue as 'Pending'.&amp;nbsp;&lt;/SPAN&gt;&lt;/P&gt;
&lt;P&gt;&lt;SPAN&gt;In other words, Blue Prism does not account for worktime on a Queue Item if it is locked, processed partially, and subsequently unlocked without marking it as Completed or Exception. The 'worktime' field within the BPAWorkQueueItem Database table&amp;nbsp;only accounts for the last touchpoint of any workqueue item (the time between the Start Time of the 'Get Next Item' action and the End Time of the 'Mark Complete' / 'Mark Exception' actions)&lt;BR /&gt;&lt;BR /&gt;&lt;/SPAN&gt;Unfortunately, this means that we can't accurately determine how long it took to process a workqueue Item if it is touched (picked from the queue) multiple times.&lt;BR /&gt;&lt;BR /&gt;&lt;SPAN lang="en-US"&gt;&lt;SPAN&gt;Can an enhancement be made to the product such that the Worktime field from the BPAWorkQueueItem table accounts for all time where the item was locked?&lt;BR /&gt;&lt;/SPAN&gt;&lt;/SPAN&gt;&lt;BR /&gt;Thank You&lt;/P&gt;&lt;BR /&gt;&lt;BR /&gt;------------------------------&lt;BR /&gt;Nicolas Payeur&lt;BR /&gt;Manager&lt;BR /&gt;Reveal Group&lt;BR /&gt;America/New_York&lt;BR /&gt;------------------------------&lt;BR /&gt;</description>
      <pubDate>Wed, 23 Sep 2020 16:24:00 GMT</pubDate>
      <guid>https://community.blueprism.com/t5/Product-Forum/Workqueue-Item-Total-Worktime-Limitation/m-p/63858#M16727</guid>
      <dc:creator>nicolas.payeur</dc:creator>
      <dc:date>2020-09-23T16:24:00Z</dc:date>
    </item>
    <item>
      <title>RE: Workqueue Item - Total Worktime Limitation</title>
      <link>https://community.blueprism.com/t5/Product-Forum/Workqueue-Item-Total-Worktime-Limitation/m-p/63859#M16728</link>
      <description>If you use Defer instead of Unlock Item, it will count towards the total work time. If you don't want to actually defer the item to a later time, use &lt;CODE&gt;Now()&lt;/CODE&gt; for the 'Until' parameter on Defer. This does have the side effect of resetting the item attempts, however.&lt;BR /&gt;&lt;BR /&gt;------------------------------&lt;BR /&gt;Nicholas Zejdlik&lt;BR /&gt;RPA Developer&lt;BR /&gt;------------------------------&lt;BR /&gt;</description>
      <pubDate>Thu, 24 Sep 2020 13:04:00 GMT</pubDate>
      <guid>https://community.blueprism.com/t5/Product-Forum/Workqueue-Item-Total-Worktime-Limitation/m-p/63859#M16728</guid>
      <dc:creator>NicholasZejdlik</dc:creator>
      <dc:date>2020-09-24T13:04:00Z</dc:date>
    </item>
    <item>
      <title>RE: Workqueue Item - Total Worktime Limitation</title>
      <link>https://community.blueprism.com/t5/Product-Forum/Workqueue-Item-Total-Worktime-Limitation/m-p/63860#M16729</link>
      <description>Hi Nicolas,&lt;BR /&gt;&lt;BR /&gt;There is a place you can raise enhancement/new feature suggestions to Blue Prism product team directly :&lt;BR /&gt;&lt;BR /&gt;&lt;A href="https://community.blueprism.com/ideas" target="test_blank"&gt;https://community.blueprism.com/ideas&lt;/A&gt;&lt;BR /&gt;&lt;BR /&gt;Take a look at existing ideas and suggestions and see if your wanted feature has already been mentioned by anyone...&lt;BR /&gt;&lt;BR /&gt;Cheers,&lt;BR /&gt;&lt;BR /&gt;------------------------------&lt;BR /&gt;Henry Li&lt;BR /&gt;------------------------------&lt;BR /&gt;</description>
      <pubDate>Sat, 26 Sep 2020 12:37:00 GMT</pubDate>
      <guid>https://community.blueprism.com/t5/Product-Forum/Workqueue-Item-Total-Worktime-Limitation/m-p/63860#M16729</guid>
      <dc:creator>henrynli</dc:creator>
      <dc:date>2020-09-26T12:37:00Z</dc:date>
    </item>
  </channel>
</rss>
