    <title>topic Hi Dave,
Thank you for your… in Product Forum</title>
    <link>https://community.blueprism.com/t5/Product-Forum/Scheduled-tasks-are-missed/m-p/54612#M9104</link>
    <description>Hi Dave,
Thank you for your answer! We are on version 6.2.1, so probably that's the reason.
However, the problem has appeared recently,&amp;nbsp;earlier we did not complain about it.
Thanks,
Michał</description>
    <pubDate>Wed, 16 Jan 2019 13:48:00 GMT</pubDate>
    <dc:creator>MichałKrzysik2</dc:creator>
    <dc:date>2019-01-16T13:48:00Z</dc:date>
    <item>
      <title>Scheduled tasks are missed</title>
      <link>https://community.blueprism.com/t5/Product-Forum/Scheduled-tasks-are-missed/m-p/54610#M9102</link>
      <description>Hello everyone,

Since few days ago, we observed abnormal situations of scheduled tasks:


	Even though the scheduled sessions are active and resource connection to BP serves status is €œYes €“ Connected€&amp;#157; the tasks are missed €“ the session does not even show up in control room,
	The scheduled runs are occasionally missed. Also €œRun Now€&amp;#157; task function doesn€™t work, however if I drag process manually to resource and run it works fine,
	The control room has slower performance as usual.


Has anyone experienced such behaviour before?</description>
      <pubDate>Tue, 15 Jan 2019 18:40:00 GMT</pubDate>
      <guid>https://community.blueprism.com/t5/Product-Forum/Scheduled-tasks-are-missed/m-p/54610#M9102</guid>
      <dc:creator>MichałKrzysik2</dc:creator>
      <dc:date>2019-01-15T18:40:00Z</dc:date>
    </item>
    <item>
      <title>Hi,
What version of BP are…</title>
      <link>https://community.blueprism.com/t5/Product-Forum/Scheduled-tasks-are-missed/m-p/54611#M9103</link>
      <description>Hi,
What version of BP are you guys on?
This was a known issue in several versions of BP, including 6.2.1 and 6.3.0. Blue Prism came out with updates for BP 5 (not sure the versions there) &amp;amp; BP 6 (I think 6.2.2 and 6.3.1) to address Scheduling issues. After that 6.3.2 improved connectivity which also affected Scheduling.
If you're using an earlier version, I'd recommend upgrading to 6.3.2 or 6.4, which I believe contains the updates that came with 6.3.2.
Respectfully,
Dave</description>
      <pubDate>Wed, 16 Jan 2019 11:29:00 GMT</pubDate>
      <guid>https://community.blueprism.com/t5/Product-Forum/Scheduled-tasks-are-missed/m-p/54611#M9103</guid>
      <dc:creator>david.l.morris</dc:creator>
      <dc:date>2019-01-16T11:29:00Z</dc:date>
    </item>
    <item>
      <title>Hi Dave,
Thank you for your…</title>
      <link>https://community.blueprism.com/t5/Product-Forum/Scheduled-tasks-are-missed/m-p/54612#M9104</link>
      <description>Hi Dave,
Thank you for your answer! We are on version 6.2.1, so probably that's the reason.
However, the problem has appeared recently,&amp;nbsp;earlier we did not complain about it.
Thanks,
Michał</description>
      <pubDate>Wed, 16 Jan 2019 13:48:00 GMT</pubDate>
      <guid>https://community.blueprism.com/t5/Product-Forum/Scheduled-tasks-are-missed/m-p/54612#M9104</guid>
      <dc:creator>MichałKrzysik2</dc:creator>
      <dc:date>2019-01-16T13:48:00Z</dc:date>