Hi Folks,

From the past two days we are facing one issue with the scheduler.We have the Process which Starts at 6:30AM  it's doing good Evryday with the schedule time but don't know what happen suddenly it's showing one more schedule with the same process at 12:15:01 Pm but i couldn't find that schedule in in Blue prism and don't know from where it's adding.Whn i click on the View Scheduke for 12:15:01 Pm it's bringing me back to the Original Schedule at 6:30 AM.

How did we resolve this issue?

Can we see from where it's adding the Schedue time as 12:15:01 Pm?

Can we see in Blue Prism data base who's creating this schedule?


------------------------------
SYED FAHEEM
Project Engineer
Wipro Limited
Asia/Kolkata
------------------------------
3 REPLIES 3

jegendra
Staff
Staff
Hi Syed,

You can see the details of owner of the scheduler and relevant activities from the Audio Logs which can be accessed via  Blue Prism System > Audit > Audit Logs.

------------------------------
Jega Avinasinathan
Customer Support Engineer
Blue Prism
------------------------------
Jega Avinasinathan Customer Support Engineer Blue Prism

VivekGoel
Level 10
Go through Audit and Scheduler logs to troubleshoot this.

Also appreciate if you can share your findings.

------------------------------
Vivek Goel
RPA Architect
Asia/Singapore
+6594554364
https://www.rpatools.com/
------------------------------

JerinJose
Level 10
HI Syed,

Please check the time format setting of your application server. probably that's causing issue.


------------------------------
Jerin Jose
RPA Product SME
EY