​Hi,

I have implementes Work Queues for bulk data process and used one resource pc. How this woks in a productions sysstem where more than one machice connected to same control room. How to map same process to multiple resouces?

------------------------------
Sidramappa Hunashyal
SA
Accenture
Asia/Kolkata
------------------------------
1 REPLY 1

Hi, Sidramappa,

you just run it on another Runtime Resource as you run it on the first one. Get Next Item action will take care of item not being taken twice. So if you do it manually now - drag and drop process to your one resource - you just do it the same way for the second resource and that's it.

Regards,

------------------------------
Zdeněk Kabátek
Head of Professional Services
NEOOPS
http://www.neoops.com/