Can't we import complete BP Release package from Command Prompt
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
21-06-17 04:10 PM
Hi Team,
when I try to import a complete BP release package from command Prompt I get the following error
'This is not a valid process definition' error when importing a release package using an AutomateC command line"
so is there any way I can import the complete package from command prompt as a package??
Regards,
Manoj
7 REPLIES 7
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
21-06-17 05:02 PM
No there isn't. Importing a release is potentially complex given the number of potential entities, conflicts and user decisions. Importing a single process or object is more of an 'atomic' function suited to the command line.
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
21-06-17 07:38 PM
Hi John,
thanks for the update.
but still I am facing issue when I export components individually as well.(not for process and object)
like for Workqueue ,environment variables, schedulers .
how do I export and import these items individually
thanks
Manoj
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
21-06-17 11:03 PM
You can't do that either Manoj I'm afraid. Those kind of items have to be done as a release and a release can only be imported manually at present. Automating the import of a release into Prod is risky - imagine if the automation allowed something into Prod that brought down all existing processes? You could get fired!
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
22-06-17 11:50 AM
Hi John,
thanks for the response.
Ya that's true but what if we have more than 4 to 5 environments where we need to spend time in exporting and importing that's really time consuming..
so my team thought of an idea y cant we automate this stuff through command prompt.so that reduces manual effort.
so are you sure there is no commands exist for importing or exporting environment variables manually???that's bit surprising .
thanks,
Manoj
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
22-06-17 03:29 PM
Definately no command for exporting/importing releases or environment variables. A full list of command line options available is in the product help - so if you cannot see it in there it does not exist.
There is an ideas and enhancements thread on this Portal - you can add this as a suggestion there.
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
22-06-17 03:58 PM
hi Denis,
Thanks for your updates
Regards,
Manoj
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
16-10-17 08:57 PM
Hi Denis,
We are also started researching on automating the release management process using AutomateC.exe. Is there is any update on importing/exporting complete BP release using AutomateC.exe(cmd line)
Thanks,
Sai