07-07-17 04:51 PM
I have to run my processes in accordance with some schedule. I've made a schedule and task. Then assigned those processes to a local machine in Task (screen "Tasks"). But my processes don't star automatically.
Does anyone have the same problem?
Thank you in advance!
3 REPLIES 3
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
07-07-17 07:35 PM
Hi Shkavro,
What do you mean by ""local machine"". Have you started a BP process as public resource?
Have you read the Guide to the Scheduler? It might be useful for you. You cam download it from the portal from Learning/Guides section.
Regards,
Tomek A.
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
07-07-17 07:53 PM
Hi Shkavro,
What do you mean by ""local machine"". Have you started a BP process as public resource?
Have you read the Guide to the Scheduler? It might be useful for you. You cam download it from the portal from Learning/Guides section.
Regards,
Tomek A.
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
08-07-17 11:54 AM
Hi, TomekA,
Yes, o'course, I've published my processes and they were available in the control room.
By ""local machine"" I mean that I developed my processes on my PC and wanted to test, how they will run in accordance with the schedule. So, I've assigned processes in Task to my PC.
No, I haven't read this guide, but I will.
Thank you for reply!