Scheduler process is not run as expected

ThulasiramP
Level 3
Hi,  I want to run blue prism process via blue prism control room through schedulers  so i have created one scheduler for one of the process particular time. But it is not running that time. So i am digging few ways , i thought my local blue prism is not started in services , so i am start blue prism services in services menu it is giving  below error. "The Blue prism server services on local computer started and the stopped . some services stop autimatically if they are not in use by other services or programs "   Anyone could please help on above issue.      Thanks in advanced.     BR, Thulasi
1 REPLY 1

John__Carter
Staff
Staff
For the scheduler to work the client and resource machines need to be connected to the DB via BP server (ie the service running on the application server).