Hello,

This week I finally got to experience real Next Gen.

I am trying out the operations based on what I learned in Blue Prism University.

I imported a very simple process, and tried to run it, but the process status remains "created", and does not run.

Please tell me the correct steps to run the process.

sumire_0-1747810509389.png

 

------------------------------
Mitsuko
Asia/Tokyo
------------------------------
1 REPLY 1

Hi @sumire 

If the process status remains "created" and does not run, you may need to ensure that the process is properly published and executed within the Blue Prism Control Centre.

You can find detailed steps on how to run a process in the Control Centre by referring to the official documentation below.

https://docs.blueprism.com/en-US/bundle/next-generation/page/control-center/rpa-processes.htm 

Best Regards,
Sayeed Bin Abdullah