100+ process Monitoring in Control
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
13-12-20 01:32 PM
How to monitor 100+ processes in BP control room without any mistake.
As it is difficult for couple of resources to keep an eye on 100+ live processes running in control room.
Please provide the methods or approaches use to ease the work for resources.
Please forward this to other group and get suggestions.
------------------------------
Jatin Kalra
Manager
Genpact
Noida UP
------------------------------
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
14-12-20 09:35 PM
RPASupervisor ;).
Regards,
------------------------------
Zdeněk Kabátek
Head of Professional Services
NEOOPS
http://www.neoops.com/
Europe/Prague
------------------------------
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
25-06-21 01:05 AM
------------------------------
Emerson Ferreira
Sr Business Analyst
Avanade Brasil
+55 (081) 98886-9544
If my answer helped you? Mark as useful!
------------------------------
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
24-09-24 06:05 PM
Hello, did you found any solution for this
Please help i also facing issues while monitoring, always missing something
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
25-09-24 09:58 AM
Hi,
As per my knowledge, Dynamic Resource Manager (DRM) can somehow help in easing the Control room tasks such as Running process as required by the business without fail, Schedule fail handling etc.
I don't have much knowledge on DRM but just saying as heard the word earlier.
Srihari
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
25-09-24 08:23 PM
@abhiramreddy As zdenek said, the answer is RPA Supervisor (now called C TWO) or some similar product that orchestrates Blue Prism automations.
Dave Morris, 3Ci at Southern Company