Excel integration
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
11-11-19 10:25 AM
If Suppose there is excel having 50 records, 40 records are processed properly and last 10 records are not processed properly then how you re run your Process in Blue Prism, so that only last 10 records are processed properly
------------------------------
Pallavi Moharir
------------------------------
------------------------------
Pallavi Moharir
------------------------------
1 REPLY 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
12-11-19 06:03 AM
use work queue.
you queue your excel records to work queue and when you process queue item, item is marked as completed or error.
after that you process items that marked as error again.
hope you understand my poor english.
------------------------------
Mitsuko
Asia/Tokyo
------------------------------
you queue your excel records to work queue and when you process queue item, item is marked as completed or error.
after that you process items that marked as error again.
hope you understand my poor english.
------------------------------
Mitsuko
Asia/Tokyo
------------------------------
------------------------------
Mitsuko
Asia/Tokyo
------------------------------
Mitsuko
Asia/Tokyo
------------------------------
