Scheduler is running but process was not executing

sumitsharma1
Level 3
Error log : "scheduler is running but process was not executing in blue prismTask: New Schedule - New Task threw an exception: Resource BDHW12B1 was unavailable: The state given was: InUse"
1 REPLY 1

John__Carter
Staff
Staff
It sounds like the resource was already running another process when the scheduler tried to use it to run your process.