29-09-21 12:35 PM
We have around 750 schedules in Blue Prism (version 6.10), but only a few hundred active schedules. Still, when we are trying to open schedules, most of the times Blue Prism stops responding. If you are lucky enough to open schedules, it takes forever.
Has anyone encountered something similar, and if so, how did you solve it?
I have tried manually deleting a large number of rows from the tables BPAScheduleLog and BPAScheduleLogEntry, but with no visible effect.
Update: Based on John's answer, I tried connecting directly to the database, rather than going via the application server. This actually made it possible to show the schedules (albeit not a lightning fast speeds). This indicates that the problem lies in the connection to the application server. I will see if I can find out more about this and update my post with what I find.
30-09-21 10:29 AM
05-10-21 04:20 AM