​Hi,

I have implementes Work Queues for bulk data process and used one resource pc. How this woks in a productions sysstem where more than one machice connected to same control room. How to map same process to multiple resouces?

------------------------------
Sidramappa Hunashyal
SA
Accenture
Asia/Kolkata
------------------------------
1 REPLY 1

Carl__Carter
Staff
Staff
Hi,

If you have not already done so, it would be worthwhile completing the Blue Prism Foundation training which is available through the Blue Prism University. Also, a read through the Advanced Work Queues guide will help.

Assuming you have available Blue Prism licenses, then a Process can be run on multiple Resource PCs simultaneously. It's just a case of starting the process on the relevant Resource PCs.

------------------------------
Carl Carter