I want to run a second process immediately from Scheduler when first terminates or aborts if an exception comes, is there any way or solution to it?
3 REPLIES 3

Anonymous
Not applicable
Help on Scheduler

Hi MehulS, Yes, it's possible, you need to set the second process as the next task after the initial task in the Scheduler. Please, have a walk through the scheduler guide http://portal.blueprism.com/system/files/2017-09/Blue%20Prism%20-%20Gui… provided by Blue Prism.  

Apologies for the wrong information, currently you can't as the Scheduler will abort if your first process in the schedule fails. Alternatively, you can handle that at a process level, where you have an exception handling block to recover & catch some exceptions that can't be bubbled up (e.g exceptions on the main page) to trigger the alternative process otherwise terminate the process (indirectly terminating the schedule).