Hi,
I just tried to run a process on two runtime resources. The issues is that it does not work as I expected.
Anyone able to tell me whether do I anything wrong or my expectations are wrong?
Scenario:
I have one schedule and one task in it. The task runs Login process. I have 3 runtime resources and 2 licenses. I use "Run now" to run the schedule on requst.
Case 1) In the task I assigned the Login process to all 3 robots (3 scheduled sessions)
Expectations: Not really sure.
Result: nothing happens. No message that anything is wrong.
Case 2) In the task I assigned the Login process to 2 robots (2 scheduled sessions)
Expectations: The process would be started on two robots.
Result: It starts on first resource. Even if I changed the order of sessions that first in is the one on robot2.
Case 3) In the task I assigned the Login process to 2 robots as 3 sessions. 2 sessions for robot2 and 1 for robot 1.
Result: It runs as expected in Case 2). Login runs on two resources.
Did I miss anything in the documentation?