Hi, Blue prism work queue guide says that you cannot change the priority of a work queue item after adding in the work queue (page no 14 of Work queue guide). But in practical we can change this by using the "Set Priority" action of the internal work queue object. Is this a defect in the product or problem in the documentation?  
2 REPLIES 2

John__Carter
Staff
Staff
I think you're right Nitesh, the Set Priority function wasn't available when the guide was first created. I'll see that the guide is updated, thanks.

NiteshGoyal
Level 3
Thanks John! so we can change the priority after adding the item.