Hello! I have this issue:

I schedule a process to run on a resource pool. Blue Prism choose to start Login Agent on BOT1 and after it logged in successfully without any errors, Blue Prism tries to start the main process on BOT2 that is in logged off state. Therefore, the main process ran with errors.

Can anyone please suggest how I should be configuring it? 

Thanks!

------------------------------
Jun Xiang Ang
------------------------------
1 REPLY 1

JerinJose
Level 10
​Resource pools is not suited for your purpose.

if you assign multiple process to same pool BP will choose the resource that is available and assign the process. and we cannot assign process to bots individually if they are part of resourcepool.
better remove the resources from pool and create a schedule with two tasks
task 1-> run login process on bot 1 and bot 2
introduce a post completion delay in task 1 configuaration
>on completion of task 1 assign main process to bot 1 and bot 2